The interior plastering work is 95 % complete in all houses. The raw installations for the building services are 90% complete and the drywall work is 80% finished. The screed work is 60% complete and the painting work is 10% complete. The green roof is 90% complete. The work on the plaster facades is 90% complete, the natural stone work 35% complete The natural stone covering has been completed in House 1. The locksmith work on the external railings is 10% complete and the dismantling of the scaffolding is 20% complete.