Construction work is progressing: rough installation almost completed, drywall and screed in the final spurt
Construction site report
04, 2024
The raw installations for the building services are 95 % complete and the drywall work is 90 % finished. The screed work is 80% complete, the painting work 20% complete and the tiling work 40% complete. The work on the plaster facades is complete and the natural stone work is 50% complete. The natural stone flooring has been completed in buildings 1 - 3. The locksmith work on the external railings is 20% complete and the dismantling of the scaffolding is 60% complete.