Building Services Installed, Drywall Nearing Completion, and More Tasks Underway
Construction site report
05, 2024
The raw installations for the building services have been completed and the drywall work is 95% finished.
The floor screed work is 95 % complete, the painting work 30 % complete and the tiling work 60 % complete. The parquet work has begun and the natural stone work is 60% complete. The natural stone flooring has been completed in buildings 1, 3, 5 and 7. The locksmith work on the external railings is 50% complete and the removal of the scaffolding is 90% complete.