The interior plastering work in all houses is almost complete (90%). The rough installations of the building services (80%) and the drywall work (70%) are also well advanced. The screed work is half complete (50%).
Painting work has already begun. The green roof is 70% complete. The plaster façades are 80% complete, while the natural stone work on the façade is still 30% complete.