Drywall and screed finished, painting and tiling work well advanced
Construction site report
06, 2024
The dry construction work is almost complete, as is the screed work. 40% of the painting work, 70% of the tiling work, 10% of the parquet work and 80% of the natural stone work have been completed. The locksmith work on the external railings is 70% complete and the removal of the scaffolding is 95% complete. The installation of the interior doors has begun.